News Construction Update | Starbucks China Coffee Innovation Park

Construction Update | Starbucks China Coffee Innovation Park

Publication Date:2023-04-25


Project Overview

Image


Project Name: Starbucks China Coffee Innovation Park

Project Location: Kunshan, Jiangsu

Building Area: 55,000.00 m²   

Building Function: Workshop, Warehousing, Logistics, Offices


Building Products: AC780 Wall System + Rock-wool Sandwich Panel System + TPO Flexible Roofing System + SS360 Roofing System

Construction Contractor: ABC


Starbucks Coffee Company was founded in 1971 and operates more than 32,000 stores across 82 markets worldwide, making it one of the world's leading specialty coffee roasters and retailers. This project represents Starbucks' largest strategic investment outside the United States. Starting here, Starbucks is building its first full coffee-industry-chain innovation base in Kunshan. Former Premier Li Keqiang personally sent a congratulatory letter expressing his best wishes for the project.


I. Project Introduction


Image


Image



The project covers 120 mu and includes five steel-structure buildings: an office building, roasting workshop, green-bean warehouse, automated high-bay warehouse, and distribution center. The entire park was designed strictly in accordance with international LEED Platinum certification standards① and China's Three-Star Green Building standards②, both at the highest certification levels, making it a model of green industrial architecture in China.


II. Project Features


The 3# green-bean storage warehouse is a high-bay facility using a flexible roofing system. Its eave height reaches 32.5 meters, ridge height 33.6 meters, and maximum single span 34 meters. Such a tall, large-span steel building presented major challenges for ABC in main- and secondary-structure installation accuracy and on-site safety management.


Image

3# Green-bean Warehouse


The walls use vertically installed four-sided tongue-and-groove rock-wool sandwich panels, placing even higher requirements on ABC's envelope-installation precision. There are many stories behind the process, but for now, take a look at the finished result↓↓↓


/ueditor/image/20260421/1776757532527193/1424a52429a01e9fdb3b0b47972ce37b.jpg

3# Green-bean Warehouse


The 2# coffee roasting plant is the core building in the campus. Its exterior uses clean, elegant metallic-gray rock-wool sandwich panels, balancing environmental performance and aesthetics. Once complete, the 2# roasting plant will be one of Starbucks' greenest coffee roasting facilities worldwide, reducing energy use and carbon emissions by approximately 20% compared with other roasting plants.


/ueditor/image/20260421/1776757577978922/93304cb6a26a047384c91828af4bf386.jpg

2# Roasting Plant


III. Construction Journey


Image

Main Structure Hoisting


Over the past year, force majeure at times made it difficult for personnel to reach the Starbucks Innovation Park project site. To maintain the delivery schedule, ABC's experienced site team adopted simultaneous installation on all four facades. At peak periods, six 25-ton truck cranes and more than 25 aerial work platforms with different boom lengths were operating on site.


Image

Progress Control for Ultra-high Wall Panels




Hard work paid off. Through the joint efforts of ABC and the owner, as of publication, steel-structure construction for Buildings 1#, 2#, and 3# in Phase I of the Starbucks China Coffee Innovation Park is essentially complete and will soon undergo acceptance and delivery on schedule. Phase II is also progressing rapidly—please stay tuned for further reports.