News Another Record | A Chronicle of Huaibei's Fastest Project

Another Record | A Chronicle of Huaibei's Fastest Project

Publication Date:2023-11-29

Image

Huaibei Yinbang - Rendering


On November 9, Yinbang (Anhui) New Energy Materials Technology Co., Ltd.'s annual 350,000-ton new-energy materials workshop project, hereafter Yinbang New Energy, entered trial production. From the arrival of steel-structure works to trial production took seven months, with Huaibei High-tech Zone and the company repeatedly witnessing the project set new industry speed records during development.


I. ABC in Action


/ueditor/image/20260420/1776677084636514/18737c9458effaca7e7c77a86e0d5f88.jpg

Huaibei Yinbang Construction Record


ABC's scope in this project includes a series of melting, casting, and rolling workshops together with supporting facilities.


Image

Main Structure Hoisting


Q:How did ABC complete the 130,000 m² Yinbang New Energy project in only seven months?

A:First, ABC maintains strong partnerships with many well-known domestic manufacturers and suppliers. As a major ABC project, letters of intent were signed with selected steel mills during the bidding stage to prioritize material supply. Second, ABC deployed a solid professional project team and increased construction personnel and mechanical equipment. Finally, ABC actively coordinated with the municipal high-tech zone's land and planning departments, organized expert reviews for major high-risk works, compressed the construction cycle, proactively supported every process, and ensured each milestone inspection was completed in time so the project could be delivered on schedule.


Image

Roof Construction


Q:The workshops contain high-temperature equipment, making the integrity of the entire roof system critically important.

A:Even under a tight schedule, ABC maintained its usual standards, ensuring thorough technical briefings and assigning technical personnel to provide full-process guidance.


Image

Wall Construction


Q:With extensive soil and stone on the project site, how did ABC keep the building facade clean and orderly?

A:There was no need to worry. Although the project uses flat sandwich panels, where even slight deformation would visibly affect the final appearance, ABC had already implemented effective protection during fabrication and transport. Dedicated forklifts rather than cranes were used for unloading, and the storage yard was kept clean, all to present the building at its best.


Image


Finally, with the trust of the owner and the High-tech Zone project team, ABC progressed from steel-structure entry on April 16 to completion of the roof and wall envelope systems. Trial production is now underway inside the workshop. The total steel-structure construction period was approximately seven months, setting the fastest industry record in Huaibei High-tech Zone.




Project Card


Image

Project Name:

Annual 350,000-ton Recycled Low-carbon Aluminum Heat-transfer Material Project — Melting & Casting Workshop and Rolling Workshop

Building Area: 134,358 m²

Location: Huaibei, Anhui Province

Building Function: Production Workshop, Warehouse

Building Products: SS360 Roofing System, Rock-wool Sandwich Panel Wall System